| Event |
DCL power glitch - event summary |
| Type of Event |
Service Interruption |
| Start Time | 10/30/09 01:00 pm |
| |
| Details |
The DCL building experienced a power glitch around noon today (Fri 10.30.09) due to a campus electrical power problem with a campus power distribution switch (DC-3) which left some buildings in the southwest area of campus without electrical power. The power has been restored by F&S in the affected buildings.
No problems were reported with CITES Data Center systems and services which run on conditioned UPS power.
CITES networking reported no networking problems within DCL.
A few people reported problems with their office PCs.
|